The Long Wait – March 17, 2023

Finally! The concrete pour for the second floor is completed. What every idea I had for a completion date is a sad joke. First, I guess I’ll go through the second-floor concrete pour. I send the week before the pour trying to add electrical outlets to the balcony area before the concrete was poured. I asked the general contractor for the name of the electrician so I can coordinate with him. Nope! No answer. It seems the contractor wanted to…

0
Read More
Column framing

Concrete Walls and Columns – October 18, 2022

The next step was the perimeter walls and the free standing columns. As we were preparing for the construction of the perimeter walls, I had ideas for making some changes in the field. Due to the City of Marathon’s illegal granting of building rights to the biggest developer in Marathon the state of Florida has stepped in to “review and comment” on all construction permits and changes to existing permits. All of the drawings were done months ago but trying…