Nope sorry, we are not done!!!! But getting closer. The drop-dead date is May 1, 2025. Six weeks away. Are we going to make it? Who knows?

The new contractor is working very hard to get things done. There needs to be people working inside and outside, at the same time. Not always happening….

Drywall Great Room

Drywall Great Room

We have drywall, painting is complete, doors are going in but everything needs constant oversight by me. Even if I pay a General Contract to do this. There is no excuse to put the wrong door in the wrong place. They have the door schedule, showing where all the doors go.

Rough grading is happening, water cistern is in and propane tank goes in tomorrow, I’m told….

Grading Up To House Elevation

Grading Up To House Elevation

Cabinets, countertops are ordered, finally!!! AC going in soon, electrician coming back on Tuesday to “finish”, but we don’t have fans or light fixtures picked out yet (after 3 years).

Kitchen Island Slab

Kitchen Island Slab

 

 

 

 

After almost 3 full years, it’s a sprint to the finish!