Yesterday there were 6 laborers working on the project! An all time high! Men were working on stripping forms, readying them for more concrete work. Other workers were readying the foundation rebar for the future horizontal foundation connectors.

Debris was removed from the site. A Bobcat was used to spread baserock around the vertical rebar foundation. Next is to ready the site to receive the concrete forms for the concrete foundation pour. That concrete will enclose the foundation of the house.

Clearing the site

Clearing the site


The site is small. There is not enough room to deliver all the baserock needed to fill the required areas at one time. So right now we are waiting for another delivery. We also need a delivery of a dumpster to remove debris; grasses, wood and paper from the Sonotubes. Hard to believe, but a dumpster costs $860/month to rent, as much as a small room rents for per month!

Placing baserock

Placing baserock


Some of the material excavated from the foundation piers will be used as material outside the house as landscape and cover for the foundation. It’s too expensive to just haul away! The rock and gravel companies make lots of money by charging for rock and gravel from people building pools and such and then sell it to people like me needing fill for foundations.