Construction work in the Florida Keys is a stop and go proposition these days. Sometimes work gets done and sometimes nothing gets done for weeks at a time. Currently there seems to be more stop than go for my project.

Foundation piers in concrete

Foundation piers in concrete

After a full day of getting the foundation rebar placed as per the designer’s plans, the work stopped. As a surprise, during this visit to the job site there as actual signs that progress was about to start up again!

The construction elves delivered base rock, 4’x8′ form board, 2″x4″s, fasteners (nails, etc.) and rebar.

In addition, the contractor scraped the soil away from the base of the vertical rebar foundation to make a better connection to the future horizontal foundation.

When that will happen I do not know, it’s the Florida Keys!