Still Slow Going – April 17, 2024

Well it’s been a difficult few months. The contractor has NOT picked up the pace, at all! So I’ve been reluctant to sit here and write about nothing happening. If I know then, what I know now, I’d choose differently, that’s for sure. In the interim I’ve been ordering things for the house, such as who will I sub out work to. I’m doing it because the contractor is so slow and is not to be moved! Too much other…

0
Read More

Well, Some Things Are Happening, But Slowly – Nov 12, 2023

Before the insulation for the walls is installed the room studs must be installed. The choice was wood or steel. Surprisingly to me, the cost is the same. I went with steel, as it is resistant to mold and termite proof. The door frames are encased in wood 2 x4″ lumber to decrease the chances of the steel, at the doors, from twisting out of plumb. The second floor ceiling is insulated with SealTite PRO Open Cell insulation. The R…

0
Read More