Walls (Latest)

Well, Some Things Are Happening, But Slowly – Nov 12, 2023

Before the insulation for the walls is installed the room studs must be installed. The choice was wood or steel. Surprisingly to me, the cost is the same. I went with steel, as it is resistant to mold and termite proof. The door frames are encased in wood 2 x4″ lumber to decrease the chances of the steel, at the doors, from twisting out of plumb. The second floor ceiling is insulated with SealTite PRO Open Cell insulation. The R…

0
Read More
Men Working Sign

So far… from being finished! – August 22, 2023

Working is so rare around here, that when it happens, they put up a sign!       After the stud lines have been placed on the concrete floors, the rough plumbing was installed. Due to the inefficient design, the second bedroom shares common walls with two bathrooms. I am hoping to add insulation or a double layer of sheetrock to deaden the bathroom sounds.   I also delivered the 3 bathroom fans and kitchen fan to be fitted as…

1
Read More

The Long Wait – March 17, 2023

Finally! The concrete pour for the second floor is completed. What every idea I had for a completion date is a sad joke. First, I guess I’ll go through the second-floor concrete pour. I send the week before the pour trying to add electrical outlets to the balcony area before the concrete was poured. I asked the general contractor for the name of the electrician so I can coordinate with him. Nope! No answer. It seems the contractor wanted to…

0
Read More
Column framing

Concrete Walls and Columns – October 18, 2022

The next step was the perimeter walls and the free standing columns. As we were preparing for the construction of the perimeter walls, I had ideas for making some changes in the field. Due to the City of Marathon’s illegal granting of building rights to the biggest developer in Marathon the state of Florida has stepped in to “review and comment” on all construction permits and changes to existing permits. All of the drawings were done months ago but trying…

1
Read More
Concrete block walls

Walls, Finally! – October 12, 2022

Well, everyone is probably bored about foundations! The next step was the perimeter walls and the free standing columns. As we were preparing for the construction of the perimeter walls, I had ideas for making some changes in the field. Due to the City of Marathon’s illegal granting of building rights to the biggest developer in Marathon the state of Florida has stepped in to “review and comment” on all construction permits and changes to existing permits. All of the…

0
Read More